"I am really pleased with the responsiveness of the staff at Klick Technology at every stage. The work was completed to a very tight timescale and was within budget. We also felt that we gained value for money."
Julie McCann - Vice Principal (Resources), Priestley College, Warrington
Conversion of 7 small rooms into Science Laboratory and Prep Room
Project Details
Disconnect existing services and make safe
Stripout of classroom and 6 old storerooms/offices
Removal of existing stud and brick dividing walls
Diamond core drilled floor to accept new services
Redundant doorway blocked up
New doorway built to suit reconfiguration of rooms
Installation of all new plumbing and electrical services
Provision for interactive services
Ceilings, flooring, lighting and decoration renewed
New furniture and 3 fixed fume cupboards fitted
Commissioning and certification of all works
Project Brief
The design for this room was still under discussion at the end of June. The College were hoping to complete the project over the summer holidays, but our order book was already full. We agreed to a completion date of mid September. The noisy stripout work was commissioned in the summer and the rest of the work was completed in termtime as agreed, with minimum disruption to the school.
The brief was to convert one small classroom and six storerooms/offices into a spacious new lab and adjoining prep room. Existing stud partition walls and a brick dividing wall had to be carefully removed. We provided a new electrical distribution board and installed Cat 2 lighting. The supply of gas, water and waste services were extended from the floor below. Flooring and decoration were renewed to complete the project.